This was stated by Minister of Restoration, Infrastructure and Transport Mykola Kalashnyk while speaking to journalists. “When I left my position as head of the Kyiv Regional Military Administration on July 16, construction of protective structures for transformers at 26 substations was 40.02% complete. Today, it stands at 55%. I take responsibility for the decisions we made while I was heading the region,” Kalashnyk said. According to him, between July 16 and October 5, the completion rate increased from 40.02% to 46.75%, representing an average rise of approximately 0.6 percentage points per week.